Key information

Endeavour Energy plans to remediate the site, replacing the roof and improving the building’s façade. These works will ensure the substation can continue to supply the region with electricity into the future.

To refurbish the building, Endeavour Energy will need to safely remove asbestos and lead paint from the site. Most of the asbestos is located inside the building, however, some asbestos-containing sealant is around the exterior windows and there is also lead paint to be removed from the exterior walls of the building.

Our qualified and experienced contractors will establish the site in December 2026, and the asbestos will be removed throughout January and February 2027. There will be some minor remediation after that, as needed.

Refurbishment works are then planned from February to August 2027.

Endeavour Energy will notify SafeWork NSW before commencing any remediation.